start:nate_6-30-2025 [2025/06/30 16:37] nbhelmsstart:nate_6-30-2025 [2025/06/30 21:59] (current) nbhelms
Line 1: Line 1:
   - Reached out to MNT GM via email, awaiting phone call   - Reached out to MNT GM via email, awaiting phone call
   - Addressed email regarding GA059 D/T resetting to 1970, location likely needs new CMOS battery   - Addressed email regarding GA059 D/T resetting to 1970, location likely needs new CMOS battery
-  - +  - emailed Cumming and Vicksburg about offline status, both experiencing internet issues that they are handling on their end 
 +  - emailed Jasper about dvr 2 being offline, awaiting response 
 +  - 26 dvr checks completed